Independent study aid. Not affiliated with or endorsed by NCEES. Always verify against the current NCEES exam specifications and reference handbook.

Water topic 14 of 18 — free theory

Stormwater Management & BMPs

Detention vs retention, sizing storage from a hydrograph, first flush and water-quality volume, outlet structures, and LID practices.

FE + PE bridgeFE Civil · Hydraulics and Hydrologic Systems (8–12)PE WRE · Hydrology (8–12)

Take the free 7-question mini-quiz ↓

Detention vs retention

The two words get mixed up constantly, so nail the distinction now:

Both flatten the outflow hydrograph. Only retention maintains a pool — if the stem mentions a permanent pool, "detention" is the wrong answer.

Sizing storage from the hydrograph

The required storage is simply the volume of inflow that arrives faster than the outlet can release it. For exam purposes the inflow is usually a triangular hydrograph and the allowable outflow is constant, which turns the whole problem into one triangle:

S = 12 (Ip − Qo) · Tb

Srequired storage volume
Ippeak inflow rate (top of the triangle)
Qoallowable constant outflow rate
Tbbase time of the hydrograph — convert to seconds before multiplying

The half comes from the triangle area; the (Ip − Qo) is the triangle's height above the outflow line. 1 acre-ft = 1,233.5 m³ if the answer wants English units.

First flush and water-quality volume

The dirtiest water arrives first: the first flush washes the accumulated oil, metals, and sediment off pavements in the opening minutes of a storm. Water-quality design therefore targets that initial slug rather than the whole storm.

The water-quality volume (WQV) is commonly sized to capture the first 25 mm (1 in.) of runoff over the drainage area:

WQV = (0.025 m) × (drainage area)

Capture the first flush, then drain it slowlyextended detention releases the WQV over roughly a day or two so particles settle

WQV is a runoff depth times an area — don't confuse it with the full design-storm volume, which is much larger.

Outlet structures

The outlet is what makes a basin a basin. Two devices do almost all the work:

Orifice:   Q = Cd · A · √(2gH)

Cddischarge coefficient, typically 0.60–0.65
Hhead measured to the centerline of the orifice

Weir (overflow/emergency):   Q = C · L · H1.5

Hhead measured above the crest

Real basins use compound outlets — a small orifice low for the water-quality release, a weir higher up for floods — so the discharge grows in stages as the pool rises.

LID at a glance

Low-impact development (LID) treats stormwater at the source instead of piping it all to one big pond. The exam tests what each practice does, not detailed design:

PE depth: routing and stage-storage-discharge

When the outflow isn't constant, the triangle shortcut won't do — use level-pool routing (the storage-indication method). Continuity on the basin reads:

dS/dt = I − O

Working from a stage-storage-discharge relationship (pool elevation → stored volume → outlet discharge), step through the inflow hydrograph interval by interval: each step's inflow minus outflow changes the storage, which sets the new stage and the next outflow. A sediment forebay at the inlet traps coarse material before it reaches the main pool, and the drawdown time (how long the WQV takes to drain) is checked so the basin is empty before the next storm.

Worked example Detention storage from a triangular hydrograph

Given:

  • Triangular inflow hydrograph: peak Ip = 3.2 m³/s, base time Tb = 90 min.
  • Allowable constant outflow Qo = 1.0 m³/s.

Solution:

  1. Convert the base time: Tb = 90 × 60 = 5,400 s.
  2. Triangle height above the outflow line: Ip − Qo = 3.2 − 1.0 = 2.2 m³/s.
  3. S = ½(2.2)(5,400) = 5,940 m³.

Answer: Required detention storage ≈ 5,940 m³.

Free 7-question mini-quiz

Stormwater Management & BMPs

Choose your answer, then check it to see the result and explanation. SI units are used unless stated otherwise.

1. A stormwater facility that maintains a permanent pool of water between storms is called a:

2. An orifice outlet has diameter 0.30 m, discharge coefficient 0.60, and 2.0 m of head above its centerline. What is the discharge?

3. A triangular inflow hydrograph peaks at 4.0 m³/s with a base time of 2.0 h. The basin releases a constant 1.5 m³/s. What storage is required?

4. The “first flush” carries the highest pollutant load, so water-quality volume is sized to capture the initial runoff — commonly the first:

5. Which low-impact-development practice is designed to let rainfall pass through the pavement surface into a stone reservoir below?

Bridge Challenge · PE-level

6. A triangular inflow hydrograph peaks at 6.5 m³/s with a 3.0 h base. The allowable release is a constant 2.0 m³/s. Compute the required detention storage in m³ and in acre-feet (1 acre-ft = 1,233.5 m³).

Bridge Challenge · PE-level

7. A detention basin must release no more than 1.2 m³/s when the head over its orifice outlet is 3.0 m (Cd = 0.62). What orifice diameter is required, and what will it actually release when the pool drains to 1.5 m of head?

Preparing for the PE Civil: Water Resources & Environmental exam?

Work the FE→PE Bridge material for this topic, then test yourself under time pressure with the 30-question Water Resources practice set — fully worked solutions and distractor analysis included.

See PE-ready practice →