Project Sitework — PE Civil (Water Resources & Environmental)

Project Sitework is the PE WRE area where design meets dirt: moving earth, grading a site so water goes where it should, keeping excavations safe and stable, and stopping construction from washing the site's soil into the nearest stream. The exam questions here are practical — volumes of cut and fill, which control goes in first, which trench needs a protective system, how a sediment basin works. If you can do earthwork arithmetic and name the right control for the situation, this area is straightforward marks.

Earthwork quantities: the average-end-area method

Most earthwork on the exam is average-end-area volume between two cross-sections a distance L apart: V = (A1 + A2) / 2 × L. Divide cubic feet by 27 for cubic yards. The common miss is forgetting the division by 2 (using the sum of the two areas) or forgetting the ft³-to-CY conversion. On a real project the sections come from a grid or from contour-difference methods, but the exam gives you the two areas directly.

Then comes the material balance:

(Try the dedicated earthwork calculator for the arithmetic.)

Site grading and layout

Grading shapes the ground so the site drains by gravity to its outlets:

Excavation safety and support

Excavation questions on the PE exam test a small set of bright-line rules:

Below the safety rules sit the support methods: sheeting and shoring (vertical members with horizontal walers and struts across a trench), soldier piles with lagging, and trench boxes that shield workers rather than hold the soil. Struts and walers carry lateral earth pressure plus any surcharge (traffic, spoil, equipment) beside the cut. Dewatering is often part of the plan — you cannot inspect, test, or compact in a flooded excavation — and it lowers pore pressures that would otherwise push on the support.

Erosion and sediment control in construction

Construction strips the land bare, and bare soil plus rain equals sediment leaving the site. The control logic is always the same:

The regulatory frame: land disturbance of 1 acre or more generally needs coverage under the construction general permit with a SWPPP (stormwater pollution prevention plan). (See Stormwater BMPs for the permanent controls that replace the temporary ones.)

Site drainage

Once graded, the site sheds water through gutters, inlets, and storm sewers:

Free 10-question mini-quiz

Project Sitework mini-quiz

Choose your answer, then check it to see the result and explanation. US customary units are used unless stated otherwise.

1. Two cross-sections 100 ft apart have cut areas of 320 ft² and 480 ft². The earthwork volume between them by the average-end-area method is most nearly:

2. A fill requires 2,400 CY measured compacted in place. The borrow soil shrinks 10% when compacted. The bank (in-place) volume that must be excavated is most nearly:

3. A silt fence run is 300 ft long. The manufacturer's limit is 0.25 acre of contributing drainage per 100 ft of fence. The maximum drainage area this fence run may serve is:

4. A trench 4.5 ft deep is excavated in ordinary soil with no hazardous atmosphere expected. Under OSHA construction rules, which statement is correct?

5. Using RUSLE (A = R·K·LS·C·P) with R = 200, K = 0.32, LS = 1.5, C = 0.05 (mulched), P = 0.9, the predicted average annual soil loss is most nearly:

6. A site is graded to fall away from a building at 2% over a horizontal distance of 150 ft. The elevation drop across that run is:

7. A 24-inch-diameter concrete storm sewer (n = 0.013) is laid at a slope of 0.005. Its full-flow capacity by Manning's equation is most nearly:

8. A contractor is about to start clearing a 12-acre site. Which construction sequence follows standard erosion-control practice?

9. Under OSHA construction rules, excavated spoil must be kept back from the edge of an excavation by at least:

10. A 2.5-acre parking lot (C = 0.90) has a time of concentration of 10 min; the IDF curve gives i = 5.5 in/hr for the design storm. The Rational Method peak discharge is most nearly: